Share to:

 

Delhi–Alwar Regional Rapid Transit System

Delhi–Alwar Regional Rapid Transit System
Overview
OwnerNCRTC
Area served
LocaleNCR
Transit type
Number of stations22
Operation
Operation will startApril 2025[1]
Headway5 - 10 minutes
Technical
System length164 km
No. of tracks2
Track gauge(1,676 mm (5 ft 6 in) broad gauge)
Electrification25 kV, 50 Hz AC overhead catenary
Average speed100 km/h
Top speed160 km/h

Delhi–Alwar Regional Rapid Transit System (Delhi–Alwar RRTS) is a 164 km long under-construction[2][3] semi-high speed rail corridor connecting Delhi, Gurgaon, Rewari and Alwar. It is one of the three RapidX corridors planned under Phase-1 of the Rapid Rail Transport System of the National Capital Region Transport Corporation (NCRTC). With maximum speed of 160 km/h and average speed of 105 km/h,[4] the distance between Delhi and Alwar will be covered in 104 minutes.[5] The project is expected to cost 37,000 crores.[6]

History

The National Capital Region Planning Board (NCRPB) as part of its Integrated Transportation Plan 2032 identified eight rail based rapid transit corridors to improve the efficacy of transportation system in the NCR.[7] These were:

  1. Delhi - Gurgaon - Rewari - Alwar
  2. Delhi - Ghaziabad - Meerut
  3. Delhi - Sonipat - Panipat
  4. Delhi - Faridabad - Ballabhgarh - Palwal
  5. Delhi - Bahadurgarh - Rohtak
  6. Delhi - Shahadra - Baraut
  7. Ghaziabad - Khurja
  8. Ghaziabad - Hapur

Of these Delhi-Alwar, Delhi-Panipat and Delhi-Meerut are to be constructed in the first phase. The Urban Mass Transit Company was given the job of conducting a feasibility study on 23 March 2010. The study thus submitted was approved by the Planning Board in 2012. The contract was then transferred to NCRTC on 18 January 2017 to carry the study forward.[1]

On 15 June 2018, the 100 km long first phase of the project from Hazrat Nizamuddin to Shahjahanpur-Neemrana-Behror, at an estimated cost of 25,000 crore, was approved by the Haryana government.[8]

Construction

Construction of Delhi-Alwar route with total 22 stations in will be completed in the following three construction phases and a pre-construction phase:[9]

  • Pre-construction phase - January 2019 to December 2019: Pre-construction activities such as Pile Loading Test and Geo-Technical Survey for one year from January 2019 to December 2019.[9]
  • Phase-1 (Delhi to Dharuhera) - January 2020 to December 2024: The 70 km Sarai Kale Khan in Delhi to Gurgaon to Dharuhera .[9] Initial 35 km with 5 stations will be underground mostly in Delhi and Gurgaon, and subsequent 71 km route with 8 stations will be overground in Haryana. To be completed by 2024.[9] In April 2020, GR Infrastructure emerged as the lowest bidder for package 1: IDPL Complex Ramp - Rajiv Chowk Ramp with 3 stations.[10]
  • Phase-2 (Dharuhera to <not updated>) - <dates>?: stations en route include Shahjahanpur, Neemrana and Behror.[9]
  • Phase-3 (Sotanala to Alwar) - <dates>?: All in Rajasthan.[9]

Stations

There will be total 22 stations in total; 16 (11 elevated and 5 underground) will be built in the first phase and the rest in later phases.[11][12][13]

No. Station Name Connections Layout Status
Phase-1
1 Sarai Kale Khan Pink Line
Hazrat Nizamuddin railway station

Sarai Kale Khan ISBT

Elevated Planned
2 INA Yellow Line Pink Line Underground
3 Munirka Magenta Line Underground
4 Aerocity (see Aerocity RRTS) Airport Express Golden Line Underground
5 Udyog Vihar Yellow Line Elevated
6 Gurgaon Sector-17 None Elevated
7 Rajiv Chowk None Elevated
8 Kherki Daula None Underground
9 Manesar None Underground
10 Panchgaon None Elevated
11 Bilaspur Chowk None Elevated
12 Dharuhera None Elevated
Phase-2
13 MBIR None Elevated
14 Rewari None Elevated
15 Bawal None Elevated
16 SNB None Elevated
17 Shahjahanpur None Elevated Planned
18 Neemrana None Elevated
19 Behror None Elevated
20 Sotanala None Elevated
Phase-3
21 Khairthal None Elevated Planned
22 Alwar None Elevated

Status updates

  • June 2018: Final Detailed Project Report (DPR) of the project is approved by the Government of Haryana.[14]
  • December 2018: The Phase-I construction project proposal for Delhi-Gurgaon-Shahjahanpur-Neemrana-Behror stretch is approved by NCRTC.
  • February 2019: The Government of Haryana approved the project.[15]
  • June 2019: The Government of Rajasthan approved the project.[15]
  • 2019 Nov: Bids for the construction of the Gurgaon section of the project were invited.
  • 2022 May: Pre-construction work begins on the project's corridor in Gurgaon.[16]
  • 2023 Mar: Pre-construction work complete in Gurgaon.[17]
  • January 2024: Phase-1 construction under way, which consists of route from Delhi to Dharuhera station only, other 4 stations till SNB which were earlier in the phase-1 will be included in the phase-2.[18][19][20] Delhi-Dharuhera section is expected to be completed by 2030.

See also

References

  1. ^ a b Stateholders' Workshop for Delhi-Gurgaon-Rewar-Alwar RRTS Corridor (PDF) (Report). Archived from the original (PDF) on 20 September 2017. Retrieved 20 September 2017.
  2. ^ "Delhi to Alwar in 104 minutes: Rapid rail proposal moves to approval stage". Hindustan Times. 22 April 2017. Archived from the original on 20 September 2017. Retrieved 20 September 2017.
  3. ^ "NHAI approves Delhi RRTS projects worth Rs53,500 crore". Livemint. 19 July 2017. Archived from the original on 20 September 2017. Retrieved 20 September 2017.
  4. ^ "Work on Delhi-Alwar RRTS to start in a year". The Tribune. Archived from the original on 20 September 2017. Retrieved 20 September 2017.
  5. ^ "Delhi-Rewari-Alwar RRTS project discussed with stakeholders today". Press Information Bureau, Government of India. Archived from the original on 21 September 2017. Retrieved 21 September 2017.
  6. ^ "Rapid rail projects connecting Delhi to Alwar and Panipat get approval". Hindustan Times. 19 July 2017. Archived from the original on 20 July 2017. Retrieved 9 October 2017.
  7. ^ "Plan to create high-speed corridor for NCR". The Hindu. 24 September 2012. Archived from the original on 20 September 2017. Retrieved 20 September 2017.
  8. ^ "Haryana gives green light to high-speed rail network project". The Hindu. 15 June 2018. Retrieved 18 June 2018.
  9. ^ a b c d e f Tender floated for construction of Rapid Rail, Daily Pioneer, 25 December 2018.
  10. ^ "GR Infra Lowest Bidder for Gurgaon Section of Delhi - Alwar RRTS Line". The Metro Rail Guy. 15 April 2020. Retrieved 15 April 2020.
  11. ^ "NCRTC|Delhi-Alwar Corridor". ncrtc.in. Archived from the original on 17 February 2019. Retrieved 15 July 2018.
  12. ^ "Delhi to Rewari Alwar in just 70 minutes: Delhi-Alwar RRTS Corridor". Metro Rail News. 17 January 2022. Retrieved 14 April 2022.
  13. ^ "NCRTC | Delhi – Alwar Corridor". Retrieved 14 April 2022.
  14. ^ "Delhi-Alwar RRTS: Project Information, Tenders, Stations, Routes and Updates". Urban Transport News. Retrieved 13 May 2022.
  15. ^ a b "Delhi - Alwar RRTS - Information, Route Maps, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 3 January 2022.
  16. ^ "Pre-construction work begins on Delhi-Gurugram-SNB RRTS corridor". The Hindu. 12 May 2022. ISSN 0971-751X. Retrieved 13 May 2022.
  17. ^ "Delhi-Alwar RRTS: Pre-construction work complete in Gurugram, check latest update on Phase 1". DNA India. 4 March 2023. Retrieved 16 June 2023.
  18. ^ "Delhi-SNB-Alwar RRTS – Information, Route Maps, Fares, Tenders & Updates". The Metro Rail Guy. 24 January 2024. Retrieved 24 January 2024.
  19. ^ "Delhi-Alwar RRTS route changed". Best24News. 24 January 2024. Retrieved 24 January 2024.
  20. ^ "NCRTC proposes change in RRTS alignment, to take it along Delhi Gurgaon e-way". Hindustan Times. 13 September 2023. Retrieved 15 October 2023.
Kembali kehalaman sebelumnya