Share to:

 

Troll A platform

A view from the South East of Troll A Platform.

The Troll A platform is a Condeep gravity-based structure offshore natural gas platform in the Troll gas field off the west coast of Norway. Built from reinforced concrete, as of 2014, it was the tallest structure that has ever been moved to another position, relative to the surface of the Earth, and is among the largest and most complex engineering projects in history.[1] The platform was a televised sensation when it was towed into the North Sea in 1995, where it is now operated by Equinor. It is also the heaviest object moved and the object with the second highest displacement at 1.2 million tons[2](the object with the highest displacement is the Gullfaks C, which had a displacement approaching 1.5 million tons[3]). Troll A was towed from the afternoon 10 May 1995 until the platform was in place 17 May 1995. It was lowered to the seabed in 303 meters of water, and had penetrated 36 meters into the soil by 19 May 1995[citation needed]. It was self-supporting with no further mooring required[citation needed].

Dimensions

Continuous slip formed gravity-based structure supports under construction in a Norwegian fjord. The tower cranes delivered concrete to the support cylinders during the continuous pour of concrete to create seamless walls.

The Troll A platform has an overall height of 472 metres (1,549 ft), weighs 683,600 tons (1.2 million tons with ballast)[4] and has the distinction of being the tallest structure ever moved by mankind. The platform stands on four legs extending down to the sea floor 303 meters (994 feet) below the surface of the sea, and the leg containing the import and export risers has an elevator that takes over nine minutes to travel from the platform above the waves to the sea floor.[5]

The legs must be able to withstand intense pressures, so the walls of Troll A's legs are over 1 metre thick and are made of steel-reinforced concrete that was formed in one continuous pour – a lengthy process that takes 20 minutes per 5 cm laid. Each leg is a mathematically joined composite of several conical cylinders that flares out smoothly to greater diameters at the top and bottom, so each support is somewhat wasp-waisted when viewed in profile and circular in any cross-section (see picture at right).[5]

The four legs are joined by a "chord shortener" (not present in the picture at right), a reinforced concrete box connecting the legs that damps out any potentially destructive wave-leg resonances by retuning the legs' natural frequencies. Each leg is also sub-divided along its length into compartments a third of the way from each end which act as independent water-tight compartments. The legs use groups of six 40 metres (130 ft) tall vacuum-anchors holding them fixed in the mud of the sea floor.[5]

Construction

Troll A was built by Norwegian Contractors for Norske Shell, with base construction beginning in September 1991[6] at a cost of 4150 million NOK,[7][8] or approximately US$650 million at the time.[9] The base and the deck were built separately, and were joined in 1998 while the base was partially submerged. The base is a Condeep gravity base structure built from reinforced concrete.

The Troll platform was towed over 200 kilometres (120 mi) from Vats, in the northern part of Rogaland, to the Troll field, 80 kilometres (50 mi) north-west of Bergen. The tow took seven days.[10]

Expansion

In the autumn of 2010 the Troll A platform was expanded with a new module. This module contains living quarters and a new control room. The new control room and expanded facilities are needed to support new compressors. These compressors are needed due to the dropping reservoir pressure in the wells.

On 18 June 2013 the new support module M12 for compressors 3 and 4 was lifted on board Troll A. The increased electricity consumption of these compressors required new power cables from shore, and due to grid constraints the platform is cut off from shore power if a grid emergency arises.[11]

Operation

Gas rises from 40 wells and is exported through a number of pipes to a processing plant at Kollsnes. Troll A is scheduled to receive two additional gas compressors[when?] to increase production volume and compensate for dropping reservoir pressure in the wells.

World records

In 1996, the platform set the Guinness World Record for the largest offshore gas platform.[12]

In 2006, the 10th anniversary of Statoil's operatorship of Troll gas production was celebrated with a concert by Katie Melua held at the base of one of the hollow legs of the platform. The concert set a new world record for the deepest underwater concert, at 303 metres (994 ft) below sea level.[13]

See also

References

  1. ^ "Meet the Troll A platform, the largest object ever moved". Oil Patch Asia. Retrieved 2 January 2014.
  2. ^ "Troll A - the tallest moved structure in the world". 21 September 2015.
  3. ^ "Heaviest man-made object moved".
  4. ^ "Gas Machine - The ultimate move". Statoil. 2 October 2006.
  5. ^ a b c National Geographic Channel production, documentary 2007(?), rebroadcast 2009-10-02, 12-13:00 hrs EDST (Comcast Cable Television system)
  6. ^ "Structurae - Troll A Platform".
  7. ^ "Great Structures of Europe".
  8. ^ "Troll and Heidrun: end of an era or forerunners of a modern world?". 1995.
  9. ^ "Exchange rate, US dollar (USD)". Norges Bank.
  10. ^ Eide, Ole Jone (13 June 2022). "Troll A – giant move from fjord to field". Equinor 50 years. Norwegian Petroleum Museum. Retrieved 21 November 2022.
  11. ^ Øyvind Lie. "Troll A blir B-kunde" Teknisk Ukeblad, 27. september 2011. Accessed: 14 November 2013.
  12. ^ "Guinness World Records - largest offshore gas platform". Guinness World Records. 1996.
  13. ^ "Melua's deep sea gig sets record". BBC News. 2 October 2006.

60°40′N 3°40′E / 60.667°N 3.667°E / 60.667; 3.667

Kembali kehalaman sebelumnya