Share to:

 

Line 3 Scarborough

Line 3 Scarborough
An S-series train at the Line 3 platform of Kennedy station
Overview
StatusClosed
OwnerToronto Transit Commission
LocaleToronto, Ontario, Canada
Termini
Stations6[1]
WebsiteOfficial route page
Service
TypeLight rapid transit
SystemToronto subway
Operator(s)Toronto Transit Commission
Depot(s)McCowan Yard
Rolling stockS series
History
OpenedMarch 22, 1985 (1985-03-22)
ClosedJuly 24, 2023 (2023-07-24)[2]
Technical
Line length6.4 km (4.0 mi)[3]
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification600 V DC fifth rail
SignallingThales SelTrac CBTC
Route map
Map Line 3 Scarborough highlighted in blue
McCowan
Scarborough Centre
Midland
Ellesmere
Lawrence East
Kennedy
TTC
GO

Line 3 Scarborough, originally known as Scarborough RT (SRT), is a defunct medium-capacity rapid transit line that was part of the Toronto subway system in Toronto, Ontario, Canada.[4][5] The line ran entirely within the eastern district of Scarborough, encompassing six stations and 6.4 kilometres (4.0 mi) of mostly elevated track. It connected with Line 2 Bloor–Danforth at its southwestern terminus, Kennedy, and terminated in the northeast at McCowan. Until its closure in July 2023, the system had a ridership of 3,908,000 per year.

The rolling stock of Line 3 consisted of smaller, semi-automated, medium-capacity trains, rather than the larger heavy-rail subway trains used on other lines in the system. Designated by the Toronto Transit Commission (TTC) as the S series, these were Intermediate Capacity Transit System (ICTS) Mark I trains built by the Urban Transportation Development Corporation (UTDC). The trains were powered by linear induction motors and operate on 1,435 mm (4 ft 8+12 in) standard gauge tracks, unlike the heavy-rail subway lines and the Toronto streetcar system, which use the unique 1,495 mm (4 ft 10+78 in) Toronto gauge.

The line remained mostly unchanged from its opening in 1985 and contained two of the least-used stations in the system. Beginning in the late 2000s, Toronto City Council debated over competing plans to revitalize and expand the line, to convert its right-of-way for use by modern light rail vehicles, or to close the line and extend Line 2 Bloor–Danforth farther into Scarborough along a different route. In 2013, the council decided on a three-station extension of Line 2 to replace Line 3 along a different route. In 2016, in order to free up funds for another transit project, the city reduced the extension to include only one station,[6][7] which was set to be completed by 2026.[8] In 2019, Progressive Conservative premier Doug Ford reinstated the three-station Scarborough subway extension and committed to completing it by 2030, with all construction costs to be borne by the province.[9][10]

The TTC planned for Line 3 to cease operations in November 2023,[11] with shuttle buses running in place of Line 3 train service until the Line 2 Bloor–Danforth subway extension to the existing Scarborough Centre station opened for service, which was estimated to be in 2030.[12] However, a train derailment in July 2023 resulted in the line permanently closing four months ahead of schedule.[13][14] By March 2023, a plan existed to convert a portion of the existing right-of-way between Kennedy and Ellesmere stations into a bus right-of-way, including an additional stop at Mooregate Avenue / Tara Avenue, located near a pedestrian bridge that spans over the former Line 3 and GO Transit's Stouffville line between Eglinton Avenue and Lawrence Avenue. In 2023, the busway was targeted for completion by 2025.[15][16]

Name

From when the line opened in 1985 until 2015, it was known as the "Scarborough RT" or "SRT". The "RT" in Scarborough RT stood for "rapid transit".[17] The name Scarborough Line was used on the official TTC website and 2014 TTC Ride Guide.[18][19] In October 2013, the TTC announced plans to give the lines official numbers to help riders and visitors to navigate the system. The line is numbered 3, as it was the third rapid transit line to open in the system. New signage was installed in March 2014.[20][21][22] In 2015, the name was simplified to "Line 3 Scarborough."

History

The original Scarborough RT logo (1985–2015)
The original tiled streetcar platform can be seen at Kennedy station. This image also clearly shows the reaction rail for the linear motor between the rails, and the two inductive communications wires on either side of the plate.

In 1972, the Government of Ontario announced the GO-Urban plan to build an intermediate capacity transit system across suburban Toronto, particularly in Scarborough and Etobicoke, using the experimental Krauss-Maffei Transurban. However, KraussMaffei was forced to abandon development when the West German federal government declined further funding.[23] GO-Urban then used some of the technologies from the Transurban to develop a simpler steel-wheeled version, the ICTS system.

During this period, the TTC had been working on plans to extend its own network with a series of streetcar systems using a new and greatly enlarged streetcar design, the Canadian Light Rail Vehicle (CLRV). The Ontario government, in charge of GO Transit, was looking for a test site for the ICTS system and demanded that the TTC use it for one of their planned streetcar projects, selecting the Scarborough extension. The TTC initially refused to make the change, arguing it was both the wrong solution and that since the construction of the line had already commenced this would be a waste of money. However, as the Ontario government was providing 75 percent of the funding for the line, they changed their minds when the government threatened to cut the funding.

At Kennedy station, there are clues revealing that it was originally built for streetcar operation; it is possible to see old low-level streetcar platforms protruding under the current high-level platforms, and the loop to turn streetcars proved too sharp for safe operation of the ICTS cars, which did not have a reason to turn around, so the loop was replaced by a single-track Spanish solution-like crossover.[24] Ontario wanted to develop and promote its new technology, which had been designed for a proposed GO Transit urban service known as GO-ALRT. Changes to federal railway regulations had made the new system unnecessary for GO, so the government hoped to sell it to other transit services in order to recoup its investment.

An S-series train in its original (1985–2015) livery in 2006

The Scarborough line was formally opened (as the Scarborough RT) to invited guests on March 22, 1985, and began revenue service on March 24, 1985.[25] Three years after it opened, the TTC renovated its southwestern terminus at Kennedy station, because the looped turnaround track, designed for uni-directional streetcars under the earlier plan and not needed for the bi-directional ICTS trains, was causing derailments; it was replaced with a single terminal track and the station was thus quasi-Spanish solution, with one side for boarding and another side for alighting, though the boarding side is also used for alighting during off-peak hours, weekends and holidays.

With the line approaching the end of its useful life,[26] the TTC reduced the frequency of service in mid-September 2012 to reduce wear and tear on both the aging rolling stock and the infrastructure.

In 2015, the TTC started work on the cars to keep them operational until the line is replaced by another mode of rail technology. This included shrink-wrapping the rolling stock with a blue vinyl finish to emphasize the line's colour and displaying the number 3, a linear diagram of the Scarborough line, and the TTC logo.[27] The original "RT" logo was no longer featured on the trains, except when the Line 3 shrink wrap is removed but not re-applied yet. These were followed by interior upgrades, such as using coloured velour seating.

On December 13, 2016, Presto fare gates were installed at Lawrence East station, making all stations along this line Presto-enabled.[28]

On April 18, 2017, the TTC awarded a $6.8-million contract to Bombardier to repair corrosion damage under the floors of the S-series cars. If the problem were not rectified, there would be the risk of serious structural damage to the cars. That would have prevented the cars from lasting until 2026 when the Scarborough Subway Extension was originally scheduled to replace Line 3. The repair work required service to be reduced from 6 four-car trains down to 5.[29]

Closure

On July 24, 2023, the last car of a train on Line 3 Scarborough derailed south of Ellesmere station. There were 45 people on board, with five injuries reported.[30] The TTC closed the line while the cause of the incident was being investigated. Although the investigation and closure was expected to last several weeks, the city accelerated work to support the replacement buses.[13][31] On August 24, 2023, the TTC announced that the line would not reopen.[14] In late September 2023, the TTC explained that bolts that held the linear induction rail to the roadbed had come loose in the July incident, causing the magnetically attracted induction rail to rise up, strike and derail the last car of the train.[32]

Immediately following the derailment, replacement bus service was implemented initially by shuttle buses serving the closed stations along Line 3. On September 3, 2023, the TTC replaced the shuttle bus service with route 903 Kennedy–Scarborough Centre Express, running northbound on Kennedy Road and southbound on Midland Avenue in reserved lanes between Kennedy and Scarborough Centre stations. Unlike the shuttle service, route 903 did not serve the closed Lawrence East, Ellesmere, Midland and McCowan stations.[15] On November 19, 2023, the TTC extended eight bus routes from Scarborough Centre to Kennedy station, eliminating the need to transfer to route 903 at Scarborough Centre station.[33]

On November 30, 2023, the consulting firm Systra submitted a report to the TTC that found that, prior to the derailment, maintenance procedures on Line 3 were weak or non-existent and that track inspection staff lacked experience to understand how various defects could create an operating risk.[34]

On October 4, 2024, EllisDon began work to demolish the right-of-way between Eglinton Avenue and the north end of Ellesmere station in preparation for constructing a busway.[35]

Farewell event

A farewell event for Line 3 was hosted at Scarborough Centre station on September 23, 2023, two months after the line's closure.[36] The event featured trains, food and drinks, a photo area, and posters depicting archival photos and trivia. The following are photos from the event:

Rolling stock

The abandoned loop at Kennedy station, which became a dead-end tail track in 1988
S-series train heading north toward Lawrence East station, 2021

The 7 four-car trains used exclusively on the Scarborough line were developed by the Urban Transportation Development Corporation (UTDC), then an Ontario Crown corporation but later sold to Bombardier Transportation. The business proposal initially bore little fruit—a proposed pilot project in Hamilton was cancelled after meeting widespread public opposition, and the only other transit systems to use the technology, named the Intermediate Capacity Transit System (ICTS), at the time were Vancouver's SkyTrain and the People Mover in Detroit. After Bombardier took over UTDC, it redesigned the technology with newer, longer cars, used to expand the SkyTrain network and also for new installations across the world. ICTS was rebranded as "Advanced Rapid Transit" (ART) and became a success for the company. Later, the technology was again rebranded, this time as Innovia Metro.

One unusual feature of the ICTS cars is that they were driven by linear induction motors: instead of using conventional motors to turn the wheels, they pushed themselves along the route using alternating flat magnets reacting with the distinctive diamagnetic aluminum metal plate that ran down the centre of the tracks. This system required very few moving parts and therefore led to lower maintenance costs. When the car motors were accelerating, they actually lifted the car off the track an extremely small distance, repelling against the aluminum plate.[37] This micro-lifting prevented the truck wheels from making a solid electrical contact with the track. Instead of using the conventional method, in which motive power is supplied by a single third rail, with return current travelling through the running rails, a separate positive and negative power rail were provided on one side of the track. Regarding the accelerating trucks and the micro-lifting, the truck wheels had a somewhat larger flange than normal to keep the car inline on the track during the micro-lifting.[original research?] The linear induction motors also allowed the cars to climb steeper grades than would be possible with traditional subway technology since wheel slip was not an issue.

The trains are also able to be operated exclusively by computers, becoming one of the earliest installations of Standard Elektrik Lorenz's "SelTrac IS" system (now owned and delivered by Thales Rail Signalling Solutions), doing away with the need for a human operator. However, due to opposition from the transit workers' union and public perception, operators were retained; the union has firmly opposed driverless trains.[38] (Other systems took full advantage of the automated operation and Vancouver's SkyTrain has been automated since 1985 without incident.) The Line 3 trains had only one operator since inception.[39] In practice, the Scarborough line trains drove themselves; the operator monitored their operations and controlled the doors.[40] One of the features which was not implemented at the time of Scarborough line's opening was the automated audible-only next-stop announcement system, which was introduced in January 2008 and meant operators were no longer required to announce stops manually. These announcements feature the voice of Susan Bigioni, a TTC employee, who also voiced the announcements for the T1 series and the retired H4, H5, and H6 trains.

In December 2023, the TTC was planning to sell five trainsets to Detroit for use on the Detroit People Mover, with two trainsets being retained for preservation.[41] In June 2024, the Detroit People Mover transit system announced the purchase of the Mark I train sets and equipment from Line 3. Their transportation to and integration with the Detroit People Mover was projected to take over a year and a half. The purchase would replace the system's existing train sets with upgraded features, along with providing much-needed parts needed to keep the system functional.[42]

Track

Line 3 used 5-rail track, which a TTC document describes as follows:

Track is the 5 rail system on direct fixation and car is powered by an induction or "reaction rail" situated between the running rails at the same top of rail elevation. There are two side contacting power rails +300V and −300V respectively situated a distance of about 14 in. from the closest gauge line of one running rail.[43]

The two power rails of 300 volts positive DC and the other of 300 volts negative DC together produced 600 volts.[44]

Line 3 tracks used standard gauge rather than the broader Toronto gauge used on Line 2 Bloor–Danforth, as the ICTS design for the line would not allow for the interchange of rail equipment between lines 2 and 3 even if they were both the same gauge.[45]

Route

The train on its elevated tracks over McCowan Road between Scarborough Centre and McCowan stations in September 2005

The line followed a roughly inverted L-shaped route when viewed northwards: first from Kennedy station, paralleling the Canadian National Railway / GO Transit's Stouffville line tracks, between Kennedy Road and Midland Avenue, 4 kilometres (2.5 mi) to Ellesmere Road; then eastward between Ellesmere Road and Progress Avenue, through Scarborough City Centre to McCowan Road. The north–south section of the route, where it followed the Stouffville line tracks, is at ground level; the shorter east–west section (except for the ground-level yard) is elevated, as is the Kennedy terminus. The line dives briefly underground just north of Ellesmere station to cross under the Stouffville line tracks. After that, it is elevated towards McCowan station. Two stations, Kennedy and Scarborough Centre, have accessible elevators as those two were the busiest stations of Line 3.

From 2 a.m. to 6 a.m. (to 8 a.m. on Sundays), when Line 3 was not operating, the 302 Kingston Rd-McCowan Blue Night bus served the same area. The 302 originates at Bingham Loop, where it connects with the 322 Coxwell bus that travelled to the west, as well as Route 324 Victoria Park that runs north. From the loop, Route 302 travels east along Kingston Road to Brimley Road, then north along Brimley Road to Danforth Road, then north on McCowan Road to Steeles Avenue. With the exception of McCowan station, it does not pass near any of the rapid transit stations, though other night bus services pass near stations. Bus service was extended on Sundays because the rapid transit lines started at 8 a.m. (beginning January 3, 2016) instead of the usual 6 a.m. start. Service frequency was 30 minutes.

The frequency for this line was 4 to 5 minutes during peak periods and 5 to 6 minutes during off-peak periods.

Operations

The TTC operated five to six trains on the line with each train consisting of four cars. There are 28 cars in the Line 3 fleet.[29]

Line 3 trains could switch directions only at the ends of the line as there were no intermediate crossovers between the two termini. Thus, there could be no short turns on Line 3.[46]

In winter, during heavy snow or freezing rain, the TTC previously ran "storm trains" overnight on Line 3 to keep power rails clear of ice, and apply anti-freeze to the power rail once freezing rain starts.[47][48] However, since the winter of 2018–2019, the TTC decided to change its procedures for Line 3. Thus, about two hours before an expected storm, the TTC may have decided to shut down Line 3 and replace it with bus service.[49] Just before the storm of February 2, 2022, the TTC replaced all Line 3 trains with 25 buses.[48]

The Scarborough line's S-series ICTS trains were stored and serviced at the small McCowan Yard, located east of McCowan station. Basic maintenance was performed in this yard; for more extensive work, the cars were taken to the subway's Greenwood Yard by truck, given the train's different track gauge and propulsion system.[50][51]

Future

After studying the revitalization and expansion of Line 3 in 2006, its replacement with alternate transit (light rail versus subway) became a subject of debate in the late 2000s. As of April 2019, there are plans to replace Line 3 with the three-stop Scarborough Subway Extension of Line 2 from Kennedy station to Sheppard Avenue, with intermediate stops at Lawrence Avenue and Scarborough Town Centre. With an estimated completion between 2029 and 2030, the extension would follow a different route than Line 3. The Government of Ontario has committed to fully fund its $5.5-billion cost.[52][53] In February 2021, the TTC recommended closing Line 3 permanently by 2023 and replacing it with bus service until the Line 2 extension opens.[8] Once Line 3 is closed, portions of its right-of-way could be converted into parkland.

Revitalization and expansion

Line 3 Extension
McCowan/Sheppard
Centennial College
 
McCowan
Yard
 
McCowan

In 2006, a study was completed on the prospects of the Scarborough line.[54][55] It recommended upgrading the line to handle larger Innovia Metro Mark II vehicles, at a cost of $190 million (in 2006 dollars) with an eight-month service suspension for the upgrade and to purchase $170 million of new rolling stock.[56] Rebuilding the curve in the tunnel north of Ellesmere station would have been required to accommodate Mark II cars. (According to transit advocate Steve Munro, the need to rebuild the tunnel was discovered after the $190 million upgrade estimate was made.[57][58]) The TTC Board approved the recommended plan for the upgrades on August 30, 2006,[56] but later cancelled the plans.[59] Extending Line 2 Bloor–Danforth, either along the current route or along a different alignment directly to Scarborough Centre station, was not considered cost-effective or justifiable.

In November 2015, transportation consultant and University of Toronto professor emeritus Richard Soberman argued that it would be vastly cheaper and faster to buy new Line 3 vehicles than to replace Line 3 with an extension of Line 2 northeast from Kennedy station. He felt the cost savings would be great enough to overcome difficulties such as the incompatibility of Mark II cars with the existing line geometry and the extra cost of building a fully separated right-of-way to Sheppard Avenue, where Line 3 could connect with either a proposed extension of Line 4 Sheppard or the Sheppard East LRT.[59]

Replacement with alternate transit

Superimposed former Line 3 (grey) and the under-construction Line 2 Bloor–Danforth extension (dark green)

The TTC and the City of Toronto completed an environmental assessment in 2010 to convert the line to light rail transit and extend it to Malvern from its current eastern terminus, McCowan, with potential new intermediate stations at Bellamy Road, Centennial College's Progress Campus and Sheppard Avenue with a possible additional station at Brimley Road between the existing Midland and Scarborough Centre stations.[60]

After initially planning to include the line with the proposed Eglinton Crosstown LRT line and create a single line called the "Eglinton–Scarborough Crosstown line", Metrolinx proceeded with plans to convert the line to light rail and extend it to Sheppard Avenue with a single new intermediate station at Centennial College. The existing line would have closed after the 2015 Pan American Games and be completed in 2020. In January 2013, Infrastructure Ontario issued a request for qualifications to shortlist companies to construct both this line and the Eglinton Crosstown line.[61] The Eglinton Crosstown line was later renamed Line 5 Eglinton and officially given the colour of orange.

In June 2013, Toronto City Council again debated having the Scarborough line replaced with an extension of Line 2 Bloor–Danforth north to Sheppard Avenue along a different right of way. Metrolinx issued a letter to Toronto City Council indicating it would cease work on the Scarborough portion of the line, because its position strayed from the original LRT agreement.[62] The subway alternative would cost between $500 million and $1 billion more than converting the Scarborough line to use the same rolling stock as the Eglinton Crosstown line be so it could be a continuation of that line. The Globe and Mail reported that Scarborough councillors had argued that providing Scarborough residents with light rail, not heavy rail, treated them as "second-class citizens".

Two competing subway plans were proposed to replace Line 3. TTC chair Karen Stintz proposed extending Line 2 Bloor–Danforth to the east before turning north, with three new stations at Lawrence Avenue and McCowan Road (primarily to serve the Scarborough Hospital's General Campus), at Scarborough Town Centre and then at Sheppard Avenue East and McCowan Road, where it would connect to the Sheppard East LRT. Transportation Minister Glen Murray made an alternative proposal to extend Line 2 along the Line 3 route but have it terminate at Scarborough Town Centre. Under the Murray plan, there would be only two stations and there would be no direct connection with the then-proposed Sheppard East LRT. The Murray plan would have required the relocation of Kennedy station as a new northbound curve from the existing Kennedy station would have been too tight for subway trains. It would also have required the complete shutdown of the line during construction, something that the Stintz plan avoided.[63]

On October 8, 2013, Toronto City Council voted 24–20 to replace the Scarborough line with a three-station extension of the Bloor–Danforth subway line. Council chose the Stintz plan for the extension.[64]

In 2013, the rejected LRT proposal would have provided a 9.9-kilometre (6.2 mi) line with seven stops serving 47,000 residents within walking distance. The selected 3-stop subway extension would be 7.6 kilometres (4.7 mi) long, serving 14,000–20,000 residents within walking distance. In 2013, the LRT was estimated to cost $1.48 billion to build versus $3.56 billion for the Line 2 extension;[65] both estimates would subsequently increase.[66]

Converting Line 3 to light rail would require the complete shutdown of the line while extending Line 2 could occur without requiring a Line 3 shutdown. Circa 2013, this was promoted as a major benefit of the Line 2 extension over a conversion to light rail. At the time, the TTC estimated it could keep Line 3 operating until 2026; however, in February 2021, the TTC recommended replacing Line 3 with buses, thus eliminating that benefit.[8] A remaining benefit of the subway option is that it would eliminate the need to change trains at Kennedy station.[65]

In June 2016, city planning staff proposed the elimination of two of the three stops along the planned Scarborough Subway Extension which would have seen Line 2 Bloor–Danforth terminate at Scarborough Town Centre in order to free up funding for a proposed Crosstown East LRT line extension of Line 5 Eglinton. The eliminated intermediate stops were at Lawrence Avenue and Sheppard Avenue.[6] Subsequently, the cost estimate for the one-stop subway extension increased to $3.2 billion, leaving the Crosstown East LRT unfunded. Given the rising cost for the subway extension and the loss of funding for the LRT line, a group of city councillors led by Josh Matlow reopened the subway versus LRT debate. Matlow proposed scrapping the one-stop subway extension in order to provide funding for 24 LRT stops on two LRT lines within Scarborough. TTC CEO Andy Byford said the cost of the LRT line following the Line 3 route may have risen to as high as $3 billion because of "delays and redesign" since 2013,[67] but Brad Ross, also of the TTC, warned of "caveats around numbers and assumptions" associated with that estimate.[68] After Council's vote, Byford admitted that the cost estimates for "delays" was unnecessary,[69] which assumed the LRT's completion would be in 2026, the same date as the subway option. However, according to Michael Warren, a former TTC chief general manager, the LRT could have been completed in 2020 at a cost of $1.8 billion, an estimate not presented to City Council when it voted.[70] There was also the issue of whether there would be space for both expanded GO service and an LRT north of Kennedy station; however, Metrolinx subsequently denied there would be such a problem.[68] On July 13, Toronto City Council voted down Matlow's proposal by a margin of roughly 2 to 1.[71]

Councillor Glenn De Baeremaeker justified the subway extension saying "Scarborough residents need the same access to a subway system that everybody else already has."[72] Mayor Tory was concerned that switching from subway to LRT would delay transit improvements in Scarborough, and might not get support from senior levels of government.[73] In September 2013, Metrolinx prepared a draft report comparing the subway and LRT options concluding that the subway option was "not a worthwhile use of money." Metrolinx had declined a TTC request to give an opinion prior to City Council's July 2016 vote.[68]

In 2017, the estimated cost of the one-stop Line 2 extension was $3.35 billion, which increased to $3.9 billion by April 2019.[74] On April 10, 2019, Premier Doug Ford announced that the province would revert the extension back to the three-stop proposal at an estimated cost of $5.5 billion with an estimated completion date between 2029 and 2030.[52] Line 2 would also receive new subway trains as part of the extension to replace the existing T1-series trains.[75][76]

Replacement bus service

On April 10, 2019, Ontario premier Doug Ford announced that Line 3 Scarborough would be replaced by a three-stop extension of Line 2 Bloor–Danforth to be completed by 2030.[52][53] However, on December 10, 2020, Toronto mayor John Tory stated that Line 3 was likely to fail and be taken out of service before the Scarborough Subway Extension was completed, with the failure possibly happening several years before completion.[77] At that point, the Line 3 vehicles were 35 years old, a decade past their 25-year life expectancy, and had become unreliable and difficult to maintain, leading to reduced service and frequent service interruptions. The TTC was looking into an alternative solution of replacing Line 3 with bus service.[78]

In February 2021, the TTC recommended shutting down Line 3 permanently in 2023 and replacing it with bus service. The TTC rejected doing a third overhaul of the line because it would cost $522.4 million and might not improve its reliability. The TTC offered two bus replacement options: purchase 60 hybrid buses by 2023 for $374.8 million or reduce the number of spares for maintenance, deferring the purchase of new buses until 2027 to 2030, at a cost of $357.4 million.[8]

In April 2022, the TTC recommended that the Line 3 right-of-way between Kennedy and Ellesmere stations be converted into a 4-kilometre (2.5 mi) dedicated busway after the Line 3 closure. There would be stops along the right-of-way at Mooregate Avenue / Tara Avenue (approximately halfway between Eglinton Avenue and Lawrence Avenue), Lawrence Avenue East and Ellesmere Road. Between the proposed Ellesmere stop and Scarborough Centre station, buses would operate along Ellesmere Road and Brimley Road. Midland and McCowan stations, along with the connecting guideway, would be permanently shut down as they were deemed not usable for a busway. The busway would operate until the opening of the Line 2 Scarborough subway extension, after which its disposition was not known.[15]

By August 2023, newly elected mayor Olivia Chow had promised to build the busway, which was estimated to cost $55 million. The project is estimated to take two years to complete.[79]

By the fourth quarter of 2023, the TTC planned to set up dedicated bus lanes via Kennedy Road (northbound) and Midland Avenue (southbound) to run buses express between Kennedy and Scarborough Centre stations. Bus lanes would be painted red and transit signal priority would be implemented.[15] An additional $60 million would be required to modify the bus platforms at Kennedy and Scarborough Centre stations.[80] With the dedicated lanes, a trip between Kennedy and Scarborough Centre stations would take 17 to 22 minutes versus 15 minutes using the future busway. The duration of the same trip on Line 3 was 10 minutes.[33]

Work on the dedicated bus lanes was expected to be completed by November 19, 2023, when Line 3 had been scheduled to shut down. However, due to the derailment of a Line 3 train on July 24, 2023, the TTC decided to end Line 3 service three months earlier. The dedicated bus lanes began service on August 26, 2023, without the bus lane work having been fully completed. Up to 70 buses per hour will use the dedicated lanes.[15]

By January 2024, the estimated cost of converting the Line 3 right-of-way into a bus roadway had increased by $12 million to $67.9 mllion. Planning was 60 percent complete. If approved by city council, work would start in 2025 for completion in 2027.[81]

The TTC is implementing bus replacement service in phases as follows:[33]

Four phases of Line 3 Scarborough bus replacement service
Effective Route between Kennedy and Scarborough Centre stations[33]: 4  Travel time in minutes[33]: 19 
July 24, 2023, to August 25, 2023 The emergency Line 3 subway shuttle operated in mixed traffic via Midland Avenue, Progress Avenue, Brimley Road and Triton Road. 20–30[82]
August 26, 2023, to November 18, 2023 Route 903 Scarborough Centre Express operates in temporarily marked reserved lanes via Kennedy Road (northbound), Midland Avenue (southbound), Progress Avenue, Brimley Road and Triton Road. 18–25
November 19, 2023, until 2027 Eight TTC bus routes will be extended from Scarborough Centre to Kennedy station, saving their riders three minutes in transfer time. With the full implementation of transit priority measures, buses will run via Kennedy Road (northbound), Midland Avenue (southbound), Ellesmere, Brimley and Triton Roads. 17–22
2027–2030[81] A busway will be constructed in the Line 3 right-of-way between Kennedy and Ellesmere stations. From the busway, buses will continue via Ellesmere, Brimley and Triton Roads. 15

Reuse of infrastructure

One of the TTC's redevelopment proposals for the Line 3 lands was to convert the corridor, including the elevated section between Midland and McCowan stations, into a linear park. This proposed park would be similar to the High Line in the New York City borough of Manhattan.[83]

In May 2024, it was announced that a 4-kilometre (2.5 mi) stretch of the former Line 3 right-of-way, between Kennedy station and the closed Ellesmere station, would be converted into the "Line 3 Busway". Demolition of original track has started in 2024,[84] and construction was expected to start in 2025, with the busway planned to begin operation in 2027. The busway was planned to remain in service after the Scarborough Subway Extension opened in order to provide extra rapid transit.[85]

References

  1. ^ "Toronto Transit Commission Subway ridership – 2018" (PDF). Toronto Transit Commission. Archived from the original (PDF) on June 28, 2021. Retrieved February 27, 2022.
  2. ^ "TTC, City improving Line 3 Scarborough bus shuttle routes as train service set to permanently end". August 24, 2023.
  3. ^ "2011 TTC Operating Statistics". Toronto Transit Commission. Archived from the original on March 8, 2013. Retrieved March 10, 2013.
  4. ^ "Subway". Schedules & Maps. Toronto Transit Commission. Archived from the original on August 27, 2016. Retrieved February 3, 2017. Line 3 Scarborough has six stations
  5. ^ "Line 3 will stay closed permanently after Scarborough RT derailment". Toronto. August 24, 2023. Retrieved August 24, 2023.
  6. ^ a b Pagliaro, Jennifer (January 20, 2016). "New Scarborough transit plan 'buys peace in the land'". Toronto Star. Archived from the original on January 20, 2016. Retrieved January 20, 2016.
  7. ^ "Scarborough subway confirmed by Toronto council". Toronto Star. October 8, 2013. Archived from the original on August 3, 2017. Retrieved August 3, 2017.
  8. ^ a b c d Spurr, Ben; Pagliaro, Jennifer (February 4, 2021). "TTC recommends seven years of shuttle buses on Scarborough RT ahead of 2030 subway opening". Toronto Star. Archived from the original on February 4, 2021. Retrieved February 4, 2021.
  9. ^ "Premier Ford Unveils Transportation Vision". news.ontario.ca. Archived from the original on April 10, 2019. Retrieved August 9, 2019.
  10. ^ "Line 2 East Extension". www.ttc.ca. Archived from the original on August 9, 2019. Retrieved August 9, 2019.
  11. ^ "Here is when the last Scarborough RT train will run before line is demolished".
  12. ^ @TTChelps (June 22, 2023). "Crews were busy installing signage to help Line 3 Scarborough customers stay informed" (Tweet) – via Twitter.
  13. ^ a b Harvey, Lex (July 27, 2023). "Scarborough RT to remain closed for at least three weeks after derailment". Toronto Star.
  14. ^ a b Harvey, Lex. "TTC ends Scarborough RT service permanently". Toronto Star. Retrieved August 24, 2023.
  15. ^ a b c d e "The future of TTC's Line 3 Scarborough (SRT)". Toronto Transit Commission. September 3, 2023. Archived from the original on September 1, 2023. Retrieved September 1, 2023.
  16. ^ "Scarborough is about to lose its light rail line. The city's replacement plan has alarmed residents". Toronto Star. May 1, 2023. Archived from the original on May 2, 2023. Retrieved May 2, 2023.
  17. ^ "Key Information About the TTC". Retrieved July 4, 2023.
  18. ^ "Subway Route Map" (PDF). Archived from the original (PDF) on August 26, 2014. Retrieved August 26, 2014.
  19. ^ "TTC Subway". Archived from the original on January 31, 2015. Retrieved January 24, 2015.
  20. ^ "TTC considers numbering subway lines | CityNews". Archived from the original on October 25, 2013. Retrieved October 23, 2013.
  21. ^ "TTC tests new numerical signage system | CTV Toronto News". March 2, 2014. Archived from the original on October 10, 2014. Retrieved July 19, 2014.
  22. ^ "New TTC Signage at Eglinton Station". Archived from the original on May 14, 2014. Retrieved July 19, 2014.
  23. ^ "GO-Urban's bright future fades suddenly". Toronto Star. November 14, 1974.
  24. ^ "Frequently Asked Questions about Toronto's Subway and the Scarborough RT – Transit Toronto – Content". Transit Toronto. Archived from the original on May 15, 2011. Retrieved December 7, 2010.
  25. ^ James, Royson (March 23, 1985). "Rapid transit line hailed at opening". Toronto Star. p. A3.
  26. ^ "Chief Executive Officer's Report – November 2012 Update" (PDF). Toronto Transit Commission. November 21, 2012. Archived (PDF) from the original on February 22, 2014. Retrieved March 10, 2013.
  27. ^ "This is what the TTC's revamped SRT cars look like". BlogTO. Archived from the original on March 8, 2015. Retrieved March 10, 2015.
  28. ^ "Presto on the TTC". Archived from the original on March 30, 2019. Retrieved March 30, 2019.
  29. ^ a b Spurr, Ben (April 18, 2017). "Scarborough RT vehicles need repairs to avoid 'catastrophic' corrosion failures". Toronto Star. Archived from the original on April 18, 2017. Retrieved April 19, 2017.
  30. ^ Casaletto, Lucas (July 25, 2023). "TTC's Line 3 shut down after train derailment; multiple passengers injured". toronto.citynews.ca. Retrieved July 30, 2023.
  31. ^ Harvey, Lex (August 17, 2023). "TTC hunts for Scarborough solutions as RT remains out of service". Toronto Star.
  32. ^ "TTC CEO says further transit closures possible after derailment of ageing SRT". Toronto Star. September 26, 2023.
  33. ^ a b c d e "Derailment Incident Overview and Operational Improvements for Bus Replacement Service" (PDF). Toronto Transit Commission. September 26, 2023. Archived (PDF) from the original on September 30, 2023.
  34. ^ "'Alarming' reports raise questions about state of Scarborough RT before crash". Toronto Star. February 22, 2024.
  35. ^ "Chief Executive Officer's Report – October 2024" (PDF). Toronto Transit Commission. October 29, 2024. p. 9. Archived (PDF) from the original on October 23, 2024.
  36. ^ "Goodbye, Line 3 Scarborough RT. TTC invites public to say farewell to a Scarborough icon". www.ttc.cahttps. Retrieved October 10, 2023.
  37. ^ Boldea, Ion; Nasar, S. A. (2001). Linear motion electromagnetic devices. Taylor & Francis. ISBN 9789056997021. Archived from the original on June 1, 2022. Retrieved November 1, 2020.
  38. ^ Bruser, David (November 17, 2006). "TTC eyes driverless subway". Toronto Star. Archived from the original on February 29, 2008. Retrieved December 8, 2007.
  39. ^ Munro, Steve (November 10, 2022). "TTC Service Changes Effective November 20, 2022 (Updated)". Steve Munro. Archived from the original on December 14, 2022. Retrieved December 13, 2022.
  40. ^ Claridge, Thomas (April 18, 1984). "First of new transit cars arrive for $196 million Scarboro line". The Globe and Mail. pp. M.3. ISSN 0319-0714.
  41. ^ "Toronto near deal to sell Scarborough RT cars to Detroit". Trains. December 20, 2023. Retrieved December 21, 2023.
  42. ^ Rahal, Sarah. "New railcars are coming to the Detroit People Mover from Toronto". The Detroit News. Retrieved June 11, 2024.
  43. ^ "Request for Information (RFI) For Rail Milling Services RFI No. R31CA15135" (PDF). Toronto Transit Commission. April 28, 2015. Archived (PDF) from the original on October 14, 2017. Retrieved June 8, 2017.
  44. ^ Bow, James (June 3, 2017). "The Scarborough Rapid Transit Line". Transit Toronto. Archived from the original on March 27, 2013. Retrieved June 8, 2017.
  45. ^ "Frequently Asked Questions About Toronto's Streetcars". Transit Toronto. Archived from the original on July 11, 2014. Retrieved May 4, 2014.
  46. ^ "TT Ride Along - Scarborough RT Rear Window". Transit Toronto. July 16, 2021. Archived from the original on December 20, 2022. Retrieved December 20, 2022.
  47. ^ "Service changes in the event of an ice storm". Toronto Transit Commission. April 16, 2018. Archived from the original on April 16, 2018. Retrieved April 16, 2018.
  48. ^ a b Iqbal, Maria (February 2, 2022). "TTC closes Scarborough Line 3 as Toronto hit by winter storm". Toronto Star. Archived from the original on December 20, 2022. Retrieved December 20, 2022.
  49. ^ "Service changes in the event of a winter storm – Streetcar". Toronto Transit Commission. Archived from the original on February 25, 2021. Retrieved February 24, 2021.
  50. ^ "McCowan Carhouse Tour". Toronto Neighbourhood Walks Project. August 1, 2011. Archived from the original on December 20, 2022. Retrieved June 7, 2017.
  51. ^ Aaron Adel & James Bow (June 25, 2015). "The Greenwood Subway Yards". Transit Toronto. Archived from the original on July 17, 2012. Retrieved December 20, 2022.
  52. ^ a b c Pagliaro, Jennifer (April 10, 2019). "Doug Ford vows 3-stop Scarborough subway. The timeline could leave riders on buses for years". Toronto Star. Archived from the original on December 21, 2019. Retrieved March 15, 2020.
  53. ^ a b "Premier Ford Unveils Transportation Vision". news.ontario.ca. Archived from the original on April 10, 2019. Retrieved August 9, 2019.
  54. ^ "Scarborough RT Strategic Plan" (PDF). August 30, 2006. Archived from the original (PDF) on August 26, 2014. Retrieved March 9, 2012.
  55. ^ "Scarborough RT Strategic Plan – Study Report – Final Report – August 2006" (PDF). August 2006. Archived from the original (PDF) on June 25, 2008. Retrieved August 5, 2013.
  56. ^ a b "Minutes of the Previous Meeting – Board Meeting Minutes – Meeting No. 1873 – Wednesday, August 30, 2006". September 20, 2006. Archived from the original on December 8, 2015. Retrieved December 1, 2015.
  57. ^ Moore, Oliver (March 17, 2017). "What has gone wrong since the 'golden age' of Toronto transit". The Globe and Mail. Archived from the original on April 22, 2017. Retrieved April 24, 2017. Dr. Richard Soberman, former chair of civil engineering at the University of Toronto, would simply buy new rolling stock for the SRT and rebuild a bend to accommodate new vehicles.
  58. ^ Munro, Steve (March 1, 2017). "Scarborough Subway Cost Rises Again". Archived from the original on April 6, 2017. Retrieved April 24, 2017. At the time [the report] was written, the cost estimate was $360 million. ... At this point it was assumed that the larger Mark II Skytrain cars would fit through the Ellesmere tunnel, but this was optimistic.
  59. ^ a b Kalinowski, Tess (November 15, 2015). "Skip the Scarborough subway and modernize the SRT, says transit expert". Toronto Star. Archived from the original on November 18, 2015. Retrieved November 20, 2015.
  60. ^ "Extension of the Scarborough Rapid Transit & Kennedy Station Improvements". City of Toronto. May 29, 2012. Archived from the original on October 6, 2012. Retrieved March 10, 2013.
  61. ^ "Request for Qualifications Issued for the Eglinton Crosstown LRT and Scarborough LRT Lines". January 22, 2013. Archived from the original on October 5, 2013. Retrieved March 10, 2013.
  62. ^ Moore, Oliver (July 2, 2013). "Metrolinx to Toronto: Subway is yours". The Globe and Mail. Archived from the original on July 7, 2013. Retrieved July 3, 2013.
  63. ^ "Scarborough subway to be built with shortened route, Ontario announces". The Globe and Mail. September 4, 2013. Archived from the original on September 4, 2013. Retrieved September 4, 2013.
  64. ^ "Scarborough subway confirmed by Toronto council". Toronto Star. October 8, 2013. Archived from the original on August 12, 2019. Retrieved October 8, 2013.
  65. ^ a b Pagliaro, Jennifer (August 7, 2015). "Scarborough subway debate suffers from lack of facts, community groups say". Toronto Star. Archived from the original on November 21, 2015. Retrieved November 19, 2015.
  66. ^ Pagliaro, Jennifer (July 13, 2016). "Toronto city council sticks with subway, rejects Scarborough LRT". Toronto Star. Archived from the original on July 13, 2016. Retrieved July 13, 2016.
  67. ^ Pagliaro, Jennifer (June 28, 2016). "Scarborough subway versus LRT debate to return to council amid transit confusion". Toronto Star. Archived from the original on June 29, 2016. Retrieved June 30, 2016.
  68. ^ a b c Pagliaro, Jennifer (October 24, 2016). "How a bid to resurrect Scarborough LRT was killed: Analysis". Toronto Star. Archived from the original on October 24, 2016. Retrieved October 24, 2016.
  69. ^ Pagliaro, Jennifer (October 25, 2016). "Watchdog says city staff may have violated public service code over Scarborough subway advice". Toronto Star. Archived from the original on October 26, 2016. Retrieved October 24, 2016.
  70. ^ Warren, R. Michael (October 26, 2016). "Was the memo that killed the LRT deliberately misleading?". Toronto Star. Archived from the original on October 27, 2016. Retrieved October 26, 2016.
  71. ^ Moore, Oliver (July 13, 2016). "Toronto City Council approves planning for raft of transit projects". The Globe and Mail. Archived from the original on April 4, 2017. Retrieved July 14, 2016.
  72. ^ Spurr, Ben; Pagliaro, Jennifer (June 1, 2016). "Mayor Tory defends Scarborough subway extension despite new ridership data". Toronto Star. Archived from the original on June 1, 2016. Retrieved June 1, 2016.
  73. ^ Tory, John (June 27, 2016). "Why I support the Scarborough subway: John Tory". Toronto Star. Archived from the original on June 28, 2016. Retrieved June 27, 2016.
  74. ^ Pagliaro, Jennifer (April 3, 2019). "Toronto's major transit projects–where they're at and what Doug Ford might do to them". Toronto Star. Archived from the original on November 21, 2021. Retrieved February 6, 2021.
  75. ^ "Toronto Transit Commission - Request for Proposals For New Subway Trains". ttc.bonfirehub.ca. Archived from the original on October 23, 2022. Retrieved November 12, 2022.
  76. ^ Murno (October 20, 2022). "TTC Issues RFP For New Subway Trains". Steve Munro. Archived from the original on November 5, 2022. Retrieved November 13, 2022.
  77. ^ Pagliaro, Jennifer (December 10, 2020). "Scarborough RT will shut down before subway is finished, mayor says". Toronto Star. Archived from the original on December 10, 2020. Retrieved December 10, 2020.
  78. ^ "Chief Executive Officer's Report – October 2020 Update" (PDF). Toronto Transit Commission. October 22, 2020. pp. 10–11. Archived from the original (PDF) on October 18, 2020. Retrieved October 17, 2020.
  79. ^ "Shuttering of Scarborough RT means the end of a transit system that changed the city". Toronto Star. August 28, 2023.
  80. ^ Spurr, Ben (April 7, 2022). "Scarborough RT may find new life as a multimillion-dollar dedicated bus lane". Toronto Star. Archived from the original on April 8, 2022. Retrieved April 8, 2022.
  81. ^ a b "Scarborough busway may not be completed until at least 2027". Toronto Star. January 22, 2024.
  82. ^ "Scarborough RT derailment raises questions about state of repair on TTC". Toronto Star. July 26, 2023.
  83. ^ "TTC looking at making a park out of Scarborough RT". Toronto Sun. February 21, 2015. Archived from the original on January 16, 2019. Retrieved January 16, 2019.
  84. ^ "Demolition of former TTC Line 3 Scarborough RT underway". Citynews. November 4, 2024.
  85. ^ "Eglinton East Light Rail Transit – Public Consultation for the Transit and Rail – Project Assessment Process" (PDF). City of Toronto. p. 13. Archived (PDF) from the original on May 30, 2024. Retrieved May 29, 2024.
KML is not from Wikidata
Kembali kehalaman sebelumnya